📰 Project Details (Wishart Townhouse): 📰
Report Period: August 2016
Project: Parkside Wishart
Civil Construction Stage 2: Completed
Stage 1 Building Start Date: February 2016
Forecast Stage 1 Building Completion Date: November 2016
Forecast Stage 2 Building Start Date:
June 2016
Forecast Stage 2 Building Completion Date: June 2017
Current Status:
New onsite display unit (unit 7) completed
Coora Street entry landscaping, footpath and fencing completed
First set of units (units 5-8) fully completed
Roofing completed
Driveways and roadways nearing completion
Electrical, Plumbing and Air Conditioning rough-ins are well underway
Kitchens, vanities and tiling all 50% complete
Internal painting underway
Fit off trades commenced
Civil works completed for Stage 2
Unit framing underway for Stage 2
Monthly Look Ahead:
Internal trades nearing completion
Courtyard and driveway landscaping underway
External cladding and brickwork completed