📰 Project Details (Wishart Townhouse): 📰
Report Period: August 2016

Project: Parkside Wishart

Civil Construction Stage 2: Completed

Stage 1 Building Start Date: February 2016

Forecast Stage 1 Building Completion Date: November 2016

Forecast Stage 2 Building Start Date: 

June 2016

Forecast Stage 2 Building Completion Date: June 2017

Current Status:
New onsite display unit (unit 7) completed
Coora Street entry landscaping, footpath and fencing completed

First set of units (units 5-8) fully completed

Roofing completed

Driveways and roadways nearing completion

Electrical, Plumbing and Air Conditioning rough-ins are well underway

Kitchens, vanities and tiling all 50% complete

Internal painting underway

Fit off trades commenced

Civil works completed for Stage 2

Unit framing underway for Stage 2

Monthly Look Ahead:
Internal trades nearing completion
Courtyard and driveway landscaping underway

External cladding and brickwork completed

   
    
 

Author: johnsonhung

Property Investment Consultant / Finance Referral (Home Loan) / Lawyer Referral (Any Legal Requirement) / PR for Australia / Real Estate Professional / Coronis Realty (International Department) / Development Adviser / Construction Builder Referral

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s